Managing the impacts of material price fluctuation

Recent fluctuations in the prices of construction materials have threatened to wreak havoc on otherwise well-planned and well-managed home projects. Economists and industry professionals have identified numerous factors causing or contributing to these fluctuations, including COVID-19-related shutdowns and restrictions, lingering tariffs and quotas, increased construction activity among single-family homeowners, and even instances of hoarding and profiteering.

Whatever the underlying cause, material price fluctuations represent a profound and lasting risk to construction projects. These fluctuations are not only causing unanticipated spikes in construction costs but are also threatening to delay project completion dates due to material rationing or unavailability. This article explores two basic ways to manage the impacts of material price fluctuations: (i) allocating the risk and responsibility through contractual provisions; and (ii) taking proactive measures to avoid or mitigate impacts on the project.

CONTRACTUAL PROVISIONS

While extreme fluctuations in construction material prices are a relatively new phenomenon, managing fluctuations in a contract is not a novel concept. For decades, parties conducting business across borders have included provisions in their contracts addressing exchange-rate fluctuations. These provisions—which are vast, varied, and supported by a well-developed body of law—serve as excellent examples of ways in which contracting parties can consider allocating risk for fluctuations in construction material prices.

Drawing upon these examples, below is a list of approaches that parties to a construction contract can take to allocate risk for material cost fluctuations. This allocation can be applied either to material costs in general, or to specific types of materials that are particularly high risk (e.g., steel, lumber, or copper).

Contractor-at-Risk

No changes will be made to the Contract for any increases in material costs and/or any delays caused by material unavailability.

Owner-at-Risk

The Contractor is entitled to a Change Order to account for any increases in material costs and/or any delays caused by material unavailability.

Risk Splitting

The Parties mutually agree to split the cost of any increases in material costs based upon a predetermined allocation (e.g., 50:50).

Threshold Approach

The Owner or Contractor agrees to bear the risk for increases in material costs up to a predetermined threshold (e.g., 5% of the assumed cost), beyond which the risk shifts to the other party.

Trigger Provision (Allowance)

The Contractor carries the material costs at an assumed value in the Contract. If the actual costs are higher than the assumed value, the Contractor is entitled to increase the Contract Sum to reflect these costs. If the actual costs are lower than the assumed value, the savings accrue 100% to the Owner. This is similar to an Allowance in the construction industry.

Indexation Provision

The Parties mutually agree to link the cost of a particular material to an index, such as the NYSE American Steel Index, rather than to the cost being charged by an individual supplier.

Freezing Provision

The Parties mutually agree to a predetermined cost for the material or materials in question, which is paid and is not subject to change regardless of further fluctuations in the market.

Guardrail Approach

The Parties mutually agree to a predetermined cost for the material or materials in question, as well as a maximum and minimum amount that the cost of the material may fluctuate. The Contractor would bear the risk for increases beyond the maximum amount, while the Owner would bear the risk for decreases below the minimum amount.

Combination

The Parties can mix-and-match different elements from the above-listed provisions to fit their particular circumstances. For example, the Parties could agree to a 5% threshold, beyond which they share the risk on a 50:50 basis.

A43 Architecture believes in honesty and transparency, and that extends into our contract process. We will be sure to work with you and all parties involved to make sure contracts are fair and factor in the changing cost of materials. 

 

PROACTIVE MEASURES

Whether the contract addresses material price fluctuations or not, both project owners and construction professionals should consider proactive measures they can take to reduce the impact of such fluctuations on their projects. The starting point for reducing these impacts is communication. It is critical that material suppliers promptly communicate price impacts and product unavailability to the architect and general contractor, and equally critical that general contractors promptly communicate this information to the owner. If this information is not timely communicated, it will greatly narrow or eliminate the options available to address the problem.

Once the problem has been identified, the project participants should consider all available options, including unusual or creative ones. Just as important, the project participants should be flexible—and not overly rigid—when it comes to implementing these solutions. For example, as-planned sequences may need to change, contingency may need to be tapped, design features may need to be changed, and additional funds may need to be contributed, each as needed to promote the success of the project. Below are some specific solutions the parties may consider:

  • Offering “sweeteners” to the supplier to ensure performance (e.g., paying a substantial down payment, agreeing to cancellation fees, and/or promising additional work on other jobs);

  • Identifying alternative or supplemental suppliers, including those located in neighboring cities or states;

  • Direct purchasing between the owner and the supplier to reduce markup;

  • Buying out all of the needed materials early in the construction project;

  • Securing space in warehouses or lay-down yards for storage of excess materials until they are scheduled for installation; and

  • Proposing substitutions or alternates to the materials specified in the design.

CONCLUSION

Due to the uncertainty surrounding commodity price fluctuations in the construction industry, some developers may decide to suspend or postpone planned construction projects. Those who do move forward with projects in the current economic environment are assuming the risk that further fluctuations will lead to increases in construction costs, delays in the construction schedule, and/or disputes with contractors and material suppliers. However, these risks can be reduced or avoided by including provisions in the contract that fairly allocate responsibility in a manner that is mutually agreeable to the parties. Lastly, for those projects that are already underway, it is essential that the parties open a dialogue to explore ways to proactively mitigate the impact of commodity price fluctuations or material unavailability on the project.

Work With A43 Architecture

Have questions about how to manage the fluctuating prices of materials? Give the professionals at A43 a call at 307-249-8650.

 

Article Source: Managing the Impacts of Material Price Fluctuations on Construction Prices